Bally’s Chicago Scales Back Non-Casino Construction Amid VGT Expansion Dispute
Devon Keller · Aug 11, 2026

Bally’s Chicago Scales Back Non-Casino Construction Amid VGT Expansion Dispute

Construction on the hotel, event facilities, and dining venues at Bally’s Chicago $1.7 billion permanent River West casino and entertainment complex has slowed, while the casino component itself continues to move forward toward an early 2027 opening. The decision stems from an ongoing disagreement with the City of Chicago regarding the broader rollout of video gambling terminals throughout the city, and Bally’s has pointed to a possible breach of the 2022 Host Community Agreement as the key factor behind the reduced pace.
Observers note that the dispute centers on how video gambling terminals will expand across Chicago neighborhoods, and this disagreement has directly affected the timeline for completing the non-gaming elements of the project. Data from project records shows that roughly 1,500 union construction jobs now face reduced hours or temporary reassignments as crews focus resources on the casino floor and related infrastructure that remains on schedule.
Background on the Host Community Agreement
The 2022 Host Community Agreement outlined specific commitments between Bally’s and city officials, including timelines for various phases of development and provisions tied to gaming expansion across the city. Under the terms referenced in the agreement, Bally’s expected certain conditions around video gambling terminals to be met before full investment in hotel towers, event spaces, and dining areas would proceed at the planned rate. When those conditions remained unresolved, the company adjusted its construction schedule for those portions while keeping the core casino build on track.
Project documents indicate that the casino itself, which forms the centerpiece of the River West complex, will still open in early 2027 regardless of the slowdown in adjacent structures. This separation allows the gaming operation to move ahead even as negotiations over the video gambling terminal rollout continue between Bally’s representatives and city departments.
Impact on Union Jobs and Construction Pace
Union officials have reported that the reduced construction pace has already begun to affect workforce deployment at the site, with approximately 1,500 positions now operating under modified schedules. Crews that were originally slated to work on hotel foundations and event venue frameworks have seen shifts in assignments, while work on the casino gaming areas continues without interruption. The change reflects Bally’s strategy of protecting the primary revenue-generating portion of the project while the video gambling terminal issue receives further attention.

City records through July show that pending applications for additional video gambling terminals remain under review, and this backlog has contributed to the current standstill in negotiations. Bally’s has maintained that the Host Community Agreement anticipated clearer progress on these applications before major non-casino investments advanced. As a result, the company has directed resources away from those elements until a resolution emerges.
Timeline and Project Scope
The overall development encompasses a full entertainment complex valued at $1.7 billion, yet the phased approach now in place keeps the casino opening date intact. Construction teams continue to meet milestones for the gaming floor, parking structures, and basic site infrastructure, even as hotel tower work, banquet halls, and multiple dining venues experience slower progress. This measured reduction allows Bally’s to manage costs while the city addresses the video gambling terminal expansion that was part of the original 2022 framework.
Those monitoring the project note that the dispute has not altered the early 2027 target for casino operations, which remains the priority for both Bally’s and city stakeholders who anticipate associated tax revenue once the facility opens. The non-casino components, while delayed in pace, stay within the broader master plan and could accelerate again once the video gambling terminal questions reach a settlement.
Current Status as of August 2026
As of August 2026, negotiations between Bally’s and the City of Chicago over video gambling terminal expansion continue without a final resolution, and the adjusted construction schedule for non-casino elements remains in effect. Project updates released during this period confirm that casino construction has not experienced similar slowdowns, preserving the path toward the 2027 launch. Union representatives continue to track job impacts, while city planners monitor how the broader video gambling terminal rollout could influence future phases of the River West development.
Conclusion
The slowdown at Bally’s Chicago reflects a direct response to unresolved terms in the 2022 Host Community Agreement, specifically those connected to video gambling terminal growth across the city. With the casino portion still advancing toward an early 2027 opening and 1,500 union jobs operating under revised schedules, the situation highlights how gaming policy disputes can shape construction timelines even when core facility targets stay protected. Further updates will depend on progress in the ongoing discussions between Bally’s and city officials.